Friday, January 06, 2006
Previous Posts
- The finished roof is very white! It's a PVC roof ...
- Good news for computer users -- the data wiring in...
- The sheetrock has been delivered and is being stor...
- The windows have been installed in the upstairs me...
- This is a view from the Hunnewell Room into the ne...
- Under the tarps you see from the street, the mason...
- A great closeup of the slate roof work. This slop...
- A view of the new slate over the skylight.
- The windows are being replaced in the old building...
- A view from the second floor of the main stair ins...
Feb 2005 Demolition
Mar 2005 Site work and excavation
Mar 2005 Concrete footings and foundations
Mar - May 2005 Underground utilities
May 2005 Structural steel erection
Jun 2005 Interior concrete floor slabs
Jul 2005 Exterior and interior wall framing
Aug 2005 Exterior masonry and interior drywall
Sep 2005 Masonry restoration
Sep - Oct 2005 Site improvements
Oct 2005 Windows (existing building)
Nov 2005 - May 2006 Interior finishes
Jan 2006 Elevator installation
Mar - Apr 2006 Sidewalks, paving, curbing
Jun 2006 Landscaping
Jul 2006 Move back to 123 Main
Aug 2006 Grand Reopening!