Thursday, March 30, 2006

Fundraising continues!

Although the deadline has passed to purchase an engraved brick, there are still ways to donate to the cause and have your name or your loved one's name somewhere within the library (or on one of the benches outside!).

Names will be added to our donor wall beginning at $250. There are other naming opportunities as well, beginning with furniture all the way up to rooms. Contact the Library Director, Leone Cole, at 617-972-6434 for more information or visit our website at www.watertownlib.org and click on About the Library -- Construction Project.

We're almost there, but we need your help in these final months. Thank you for your support!

The mason has started cleaning the exterior brick work.

The children's room is being painted a very nice yellow color.

We're making progress on the elevator -- we now have a door!

The tile looks great in the restrooms!

Friday, March 17, 2006


These great looking light fixtures are arranged randomly upstairs over the main stair and gallery area.

Drywall continues to go up. This is the main stair.

The elevator is being installed! Permanent power was delivered to the building this week, making it possible to start the elevator installation.

Friday, March 03, 2006


Our new sign on the side of the building that faces Town Hall. We didn't forget the "public" part of our name, we just wanted it to be the same wording that is on the orginal building.

A preview of the color palatte.